come under the purview of superstructure, as mentioned in Section 2(k) of the Act, 2008. 12. The Hon’ble Apex Court in the case of M/s Brahmaputra Infrastructure Ltd. (supra), after referring Sections 8, 9 and 22 of the Act 2008 has held in paragraph-5 of the said...

Read Full Judgment Analysis →

which was to be based on a platform of 30 ft height. As such, the work performed by the petitioner in pursuance of the contract comes under the definition of ‘work contract’ defined in Section 2(k) of the Act 2008. Therefore, the Arbitration Tribunal has jurisdiction over the disput...

Read Full Judgment Analysis →

parties ====================================================== Appearance : For the Petitioner/s: Mr. S.D.Sanjay,Sr. Advodate Mr. Mohit Agarwal Mr. Rahul Kumar Mr.Vishal Kumar Ms. Priya Gupta For the State Mr. Nalin Vilochan Tiwary, AC to GA 9 For BSTDCL Mr. Kumar A...

Read Full Judgment Analysis →

the issue will be resolved by the Managing Director, Bihar State Tourism Development Corporation, Ltd. amicably. However, in case of any deadlock, Secretary Tourism Govt. of Bihar will be the sole Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 6/10 arbitrator.” 6. The learned counsel ...

Read Full Judgment Analysis →

2(k) of the Act, 2008. 12. The Hon’ble Apex Court in the case of M/s Brahmaputra Infrastructure Ltd. (supra), after referring Sections 8, 9 and 22 of the Act 2008 has held in paragraph-5 of the said Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 9/10 decision that in the absence of an agree...

Read Full Judgment Analysis →

IN THE HIGH COURT OF JUDICATURE AT PATNA CIVIL REVISION No.12 of 2021 ====================================================== Rang Vikalp registered office at Studio Variation Artists Studio Sardar Patel Colony, Patliputra Colony Telephone Exchange Road behind SIS Security Office, Kurj...

Read Full Judgment Analysis →

a sand stone statue of Lord Budha having 70 ft height in Bhumi Sparsh posture, on the platform of a height of 30 ft. The learned counsel submitted that as per the Agreement, 30 ft high platform was to be constructed first and thereon the statue of Lord Budha was to be installed. As such, ...

Read Full Judgment Analysis →

the letter sent by him is still with the Managing Director, Bihar State Tourism Development Corporation, who is Arbitrator, as per paragraph- 22 of the Agreement, which is extracted hereinbelow:- “22. In case of any difference of opinion in any item of work the issue will be resolved by the Man...

Read Full Judgment Analysis →
Manohar Lal v. State

undefined INSC 140Patnahcucisdb94 High Court (10 8)

70% Match

Biharsharif, Nalanda, where the case is pending/successor court in connection with Excise P.S. Case No. 766 of 2023, subject to the conditions as laid down under Section 438 (2) of the Cr.P.C. aditi/- (Satyavrat Verma, J) U T...

Read Full Judgment Analysis →

be referred to as ‘the Arbitration Tribunal’), in Reference Case No. 70/2016, by which the Arbitration Tribunal dismissed the reference made under Sections 9 and 11 of the Bihar Public Works Contracts Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 2/10 Disputes Arbitration Tribunal Ac...

Read Full Judgment Analysis →