Cases Citing Section 8
Statute: Arbitration and Conciliation Act, 1996 (arbitration-and-conciliation-act-1996)
undefined INSC 588 • Patnahcucisdb94 High Court (10 8)
come under the purview of superstructure, as mentioned in Section 2(k) of the Act, 2008. 12. The Hon’ble Apex Court in the case of M/s Brahmaputra Infrastructure Ltd. (supra), after referring Sections 8, 9 and 22 of the Act 2008 has held in paragraph-5 of the said...
Read Full Judgment Analysis →undefined INSC 858 • Patnahcucisdb94 High Court (10 8)
which was to be based on a platform of 30 ft height. As such, the work performed by the petitioner in pursuance of the contract comes under the definition of ‘work contract’ defined in Section 2(k) of the Act 2008. Therefore, the Arbitration Tribunal has jurisdiction over the disput...
Read Full Judgment Analysis →undefined INSC 443 • Patnahcucisdb94 High Court (10 8)
the letter sent by him is still with the Managing Director, Bihar State Tourism Development Corporation, who is Arbitrator, as per paragraph- 22 of the Agreement, which is extracted hereinbelow:- “22. In case of any difference of opinion in any item of work the issue will be resolved by the Man...
Read Full Judgment Analysis →undefined INSC 588 • Patnahcucisdb94 High Court (10 8)
parties ====================================================== Appearance : For the Petitioner/s: Mr. S.D.Sanjay,Sr. Advodate Mr. Mohit Agarwal Mr. Rahul Kumar Mr.Vishal Kumar Ms. Priya Gupta For the State Mr. Nalin Vilochan Tiwary, AC to GA 9 For BSTDCL Mr. Kumar A...
Read Full Judgment Analysis →undefined INSC 828 • Patnahcucisdb94 High Court (10 8)
2(k) of the Act, 2008. 12. The Hon’ble Apex Court in the case of M/s Brahmaputra Infrastructure Ltd. (supra), after referring Sections 8, 9 and 22 of the Act 2008 has held in paragraph-5 of the said Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 9/10 decision that in the absence of an agree...
Read Full Judgment Analysis →undefined INSC 456 • Patnahcucisdb94 High Court (10 8)
a sand stone statue of Lord Budha having 70 ft height in Bhumi Sparsh posture, on the platform of a height of 30 ft. The learned counsel submitted that as per the Agreement, 30 ft high platform was to be constructed first and thereon the statue of Lord Budha was to be installed. As such, ...
Read Full Judgment Analysis →undefined INSC 649 • Patnahcucisdb94 High Court (10 8)
the issue will be resolved by the Managing Director, Bihar State Tourism Development Corporation, Ltd. amicably. However, in case of any deadlock, Secretary Tourism Govt. of Bihar will be the sole Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 6/10 arbitrator.” 6. The learned counsel ...
Read Full Judgment Analysis →undefined INSC 560 • Patnahcucisdb94 High Court (10 8)
any of its works relating to construction, repairs or maintenance of any building or superstructure, dam, weir, canal, reservoir, tank, lake, road all types of bridge, culvert, factory or work shops or of such other work of the State Government or, as the case may be, of the public ...
Read Full Judgment Analysis →undefined INSC 661 • Patnahcucisdb94 High Court (10 8)
be referred to as ‘the Arbitration Tribunal’), in Reference Case No. 70/2016, by which the Arbitration Tribunal dismissed the reference made under Sections 9 and 11 of the Bihar Public Works Contracts Patna High Court C.R. No.12 of 2021(11) dt.12-01-2024 2/10 Disputes Arbitration Tribunal Ac...
Read Full Judgment Analysis →undefined INSC 207 • Patnahcucisdb94 High Court (10 8)
appointment letter and in his place, the respondent no. 8 was selected as Aganwadi Sevika. 4. On the other hand, the respondent no. 8 obtained only 58.60 % marks, much less than the petitioner, who obtained 76% marks, nonetheless her case was placed for consideration and, as such,...
Read Full Judgment Analysis →